Where construction AI agents live

Medical Office Buildout

Pre-Construction Planning  β€’  CM-at-Risk  β€’  45,000 SF  β€’  2026-06-09
5 Phases Β· 5 Milestones
Work Breakdown Structure β€” click a phase to expand/collapse
Pre-ConFoundationStructureMEPFinishes
Project Schedule β€” Gantt (critical path outlined, modeled ~30% underway)
Fit
Permits issued
Foundations complete
Structure topped out
MEP rough-in complete
Substantial completion
Pre-Construction & Procurement
Mar 17–May 26
Site Work & Foundations
May 26–Jun 30
Structure & Envelope
Jun 30–Aug 18
MEP Rough-In
Aug 18–Oct 20
Finishes & Closeout
Oct 20–Dec 22
Critical path MilestoneFinish-to-start dependencyToday
Responsibility Matrix (RACI)
ResponsibilityOwnerContractorArchitect
Furnish medical equipmentR
Approve change ordersR
Provide site accessR
Means & methodsR
Site safety & ICRA containmentR
Schedule & buyoutR
Design intent & RFIsR
Submittal reviewR
Code complianceR
Planning Detail

Assumptions

  • Clinic remains occupied; noise-restricted 7am–6pm
  • ICRA containment required near active clinic
  • Long-lead medical equipment owner-furnished

Risk Considerations

  • Plumbing fixture lead times
  • Infection control compliance
  • Monsoon season exterior exposure
Project Charter (Draft)
PROJECT CHARTER β€” Medical Office Buildout

Purpose: Deliver a 45,000 SF, 3-story medical office buildout for Northstar Health using CM-at-Risk, within a $8M–$10M budget and a 10–12 month schedule.

Objectives: Maintain clinic operations (ICRA), meet healthcare code, and achieve substantial completion within budget.

Sponsor: Northstar Health. Delivery: CM-at-Risk.