Executive Summary
Project is 62% complete and tracking 3 days behind on the critical path due to a plumbing fixture delay. Budget remains healthy at 58% spent. Owner action needed on RFI-042 (15 days open) to protect the floor-2 drywall start.
Work Completed
• Installed HVAC ductwork floors 2-3
• Poured concrete pad at loading dock
• Electrical rough-in 80% complete
Safety
Toolbox talk on fall protection. Zero recordable incidents this week.
Schedule Update
62% complete; 3 days behind. Recovery: add Saturday plumbing crew once fixtures arrive.
Budget Update
58% spent of $9.4M. One pending CO ($85k). Contingency at 45% remaining.
Look-Ahead
• Complete electrical rough-in
• Begin drywall framing floor 2
• Receive plumbing fixtures (June 12)