Medical Office Buildout

Northstar Health  •  Week of June 2, 2026  •  Weekly Report  •  2026-06-09
At Risk
% Complete
62%
Schedule
Behind — 3 days
Budget
On budget — 58% spent of $9.4M
Crew On Site
30
workers across 4 trades

Issues by Severity

Open Issues & Risks

PlumbingHIGH
Plumbing fixtures delayed
Threatens floor-2 finish start; 3-day risk
ScheduleMED
RFI-042 aging 15 days
Blocks final MEP coordination
BudgetMED
Pending CO fire suppression
$85k budget exposure
WeatherLOW
Monsoon season approaching
Possible July weather delays
Weather — this period
Mon
☀️
Clear 85F
Tue
🌧
Rain delay 2hrs
Wed
☀️
Clear 88F
Thu
☀️
Clear 90F
Fri
Cloudy 82F
Action Items
PriorityAction ItemOwnerDue
HIGH Expedite plumbing fixtures; confirm June 12 deliveryMechanical PMJune 11
HIGH Escalate RFI-042 to architectProject EngineerJune 10
MED Submit CO for fire suppression zone 4GC PMJune 13
LOW Schedule Saturday recovery crewSuperintendentJune 14
Report Detail

Executive Summary

Project is 62% complete and tracking 3 days behind on the critical path due to a plumbing fixture delay. Budget remains healthy at 58% spent. Owner action needed on RFI-042 (15 days open) to protect the floor-2 drywall start.

Work Completed

• Installed HVAC ductwork floors 2-3
• Poured concrete pad at loading dock
• Electrical rough-in 80% complete

Safety

Toolbox talk on fall protection. Zero recordable incidents this week.

Schedule Update

62% complete; 3 days behind. Recovery: add Saturday plumbing crew once fixtures arrive.

Budget Update

58% spent of $9.4M. One pending CO ($85k). Contingency at 45% remaining.

Look-Ahead

• Complete electrical rough-in
• Begin drywall framing floor 2
• Receive plumbing fixtures (June 12)